Acceptance Delayed, Invoice Blocked: What the Supplier Can Do

2 days ago
4 min read

Recommended action for suppliers of machinery and plant where the customer delays acceptance and payment therefore does not fall due

Under a contract for work (Werkvertrag), remuneration generally falls due only upon acceptance (Section 641(1) sentence 1 BGB). If the customer delays acceptance, the supplier cannot invoice, its liquidity remains tied up, and it continues to bear the risk. The law provides the supplier with remedies, which should be used in a particular order.

Preliminary question: contract for work or sales law?

Under Section 650(1) BGB, contracts for the supply of movable goods to be manufactured are governed by sales law. For non-fungible goods, certain provisions of the law on contracts for work apply in addition (Sections 642, 643, 645, 648, 649 BGB), with the passing of risk under Sections 446 and 447 BGB taking the place of acceptance. Whether a machinery contract is a contract for work or a contract for the supply of manufactured goods depends on the focus of the contract, for example whether assembly, installation and commissioning at the customer’s premises are owed. This analysis is the basis for all further steps. The following remarks assume a contract for work with an obligation to accept.

Starting point

The customer is obliged to accept the work if it has been produced in conformity with the contract; it cannot refuse acceptance because of immaterial defects (Section 640(1) BGB). Until acceptance, the contractor bears the risk (Section 644(1) sentence 1 BGB), and the burden of proof for performance in conformity with the contract lies with it (Section 632a(1) sentence 3 BGB). Interest on the remuneration begins to run only upon acceptance (Section 641(4) BGB). Every day of delay therefore costs the supplier liquidity and security.

Step 1: Document completion and request acceptance

The supplier should give written notice of completion, substantiate readiness for acceptance (test and functional records, trial run) and propose a specific acceptance date. This creates the basis for all further steps and secures the evidence.

Step 2: Set a reasonable deadline – deemed acceptance

Under Section 640(2) sentence 1 BGB, the work is also deemed accepted if, after completion, the contractor has set the customer a reasonable period for acceptance and the customer has not refused acceptance within that period by stating at least one defect. Upon deemed acceptance the remuneration falls due, the risk passes, and interest begins to run. The special notice in text form under sentence 2 is required only for consumers; towards businesses it is nevertheless advisable.

The period must be reasonable and should reflect the size, complexity and testing effort of the plant; for complex plant, a period of only a few days is risky. The setting of the deadline and its receipt should be provable. Note that the customer can prevent the fiction simply by stating one defect. Anyone relying on the fiction must therefore expect defects to be named and should prepare its position accordingly.

Step 3: Enforce the obligation to accept

If the customer names defects, what matters is whether they are material. For immaterial defects it could not refuse acceptance (Section 640(1) sentence 2 BGB). If it wrongfully and definitively refuses acceptance, the remuneration, according to case law, falls due even without acceptance; setting a deadline is then not required (Federal Court of Justice (BGH), judgment of 8 November 2007 – VII ZR 183/05, para. 29). The supplier must then, however, plead and prove that it has performed substantially in conformity with the contract (cf. BGH, judgment of 28 May 2020 – VII ZR 108/19).

As a rule, the customer can assert warranty rights only after acceptance (BGH, judgment of 19 January 2017 – VII ZR 235/15). Once the remuneration is due, it may withhold a reasonable portion, as a rule twice the cost of remedying the defects (Section 641(3) BGB). The remainder must be paid. This limits its leverage.

Step 4: Assert the consequences of default

If the customer is in default of acceptance, the risk passes to it (Section 644(1) sentence 2 BGB), and the supplier can claim reimbursement of additional expenses for storage and preservation, such as warehousing costs (Section 304 BGB). If the customer culpably breaches its obligation to accept, damages (Sections 280, 281 BGB) and withdrawal (Section 323 BGB) may also be considered after a deadline has been set. These remedies are drastic and carry litigation and unwinding risks. They should be used only after reviewing the individual case and the contractual position.

Contractual safeguards

The most effective protection lies in the contract itself. In addition to the statutory instalment payment (Section 632a BGB), the supplier should agree a payment schedule with milestones, such as down payment, readiness for shipment, delivery and commissioning. Under Section 632a(1) BGB it can claim instalments in the amount of the value of the services rendered and owed under the contract, which it must substantiate by a statement (sentence 5). For components that have been made and made available, this applies only if, at the customer’s option, title is transferred to it or security is provided (sentence 6). In addition, a clear definition of readiness for acceptance, fixed deadlines for the acceptance date and notice of defects, and a deemed acceptance after expiry of the deadline are recommended. In general terms and conditions, such clauses must be measured against Sections 305 et seq. BGB, in particular Section 307 BGB.

Practical checklist

  • Check whether the contract is a contract for work or for the supply of manufactured goods (Section 650 BGB) and which acceptance provisions apply.

  • Give written notice of completion and substantiate readiness for acceptance with records.

  • Set a reasonable acceptance deadline in a provable manner (Section 640(2) BGB) and point out the consequences.

  • Assess defects named by the customer for materiality and promptly remedy or reject them.

  • Document storage costs and other additional expenses from the outset.

  • In new contracts, agree a payment schedule, acceptance deadlines and deemed acceptance.

Conclusion

Remuneration depends on acceptance, and the supplier should bring it about actively: through documented completion, a reasonable acceptance deadline and, where necessary, enforcement of its rights. Better still is to limit the risk in the contract itself through instalment payments and a deemed acceptance. Please contact us if you have any questions.


As of: 23.11.2026

NIETZER Rechtsanwälte · Attorneys at Law (USA) · Heilbronn · www.unternehmensrecht.com

This article is for general information purposes only and does not replace legal advice in an individual case.