top of page

Low Water: Who Bears Delivery Risk and Extra Costs?

4 hours ago
3 min read

Late delivery, force majeure and freight costs in supply contracts – what applies when the Rhine fails as a transport route

After weeks of extremely low water, Rhine water levels are rising again. According to media reports, inland vessels could previously be loaded only in part, supply chains were disrupted and freight costs rose. Expert authorities warn against premature all-clear signals. The question remains for companies: who is liable if goods arrive late – and who pays the extra costs?

Basic principle: more expensive does not mean impossible

Under Section 275(1) BGB, the claim for performance is excluded only “to the extent that performance is impossible for the obligor or for anyone else”. Delivering at greater cost or with greater difficulty is not impossibility. A right to refuse performance under Section 275(2) BGB requires a gross disproportion between the effort required and the buyer’s interest in performance; in this assessment it also matters whether the supplier is responsible for the obstacle. Merely increased costs will as a rule not suffice.

Default: the supplier must exculpate itself

If the supplier delivers late, it owes compensation for loss caused by default only if it is responsible for the delay. Section 286(4) BGB provides: “The obligor is not in default as long as performance is not made as a result of a circumstance for which the obligor is not responsible.” Important: it is not the buyer who must prove fault, but the supplier who must prove its exculpation.

Anyone who owes generic goods (goods defined only by type and quantity) may, under the contract, have assumed a procurement risk (Section 276(1) sentence 1 BGB). It is then liable even without fault. Whether this covers transport depends on the place of performance: must the supplier deliver the goods to the customer, or only hand them over to the carrier? In addition, low water on the Rhine has occurred repeatedly for years. The more foreseeable an obstacle is, the harder exculpation becomes.

Force majeure: only as good as the clause

The BGB contains no general rule on “force majeure”. What matters is the contract. Many clauses mention natural events, but not low water expressly. They often require that the event was unforeseeable and is notified without undue delay. Anyone who fails to give notice often loses the protection of the clause.

Standard terms must be measured against Section 307 BGB even between businesses (Section 310(1) sentence 2 BGB). A clause that releases the supplier from all obligations upon any transport disruption may be invalid.

Withdrawal even without fault

Even if the supplier is exculpated, the buyer may withdraw from the contract after a reasonable period has expired without result (Section 323(1) BGB). Withdrawal does not require that the supplier be responsible.

Passing on additional costs?

Without a contractual basis, such as a price adjustment or low-water surcharge clause, the supplier in principle bears increased freight costs under a fixed price. An adjustment of the contract under Section 313(1) BGB requires a serious change and that continuing to be bound by the contract is unreasonable for one party, taking the allocation of risk into account. Risks that were foreseeable when the contract was concluded do not, as a rule, justify an adjustment.

Checklist for companies

  • Review contracts for clauses on force majeure, transport disruptions and price adjustment.

  • Clarify the place of performance and the delivery term (e.g. Incoterms).

  • Notify obstacles without undue delay and in documented form.

  • Examine alternative transport routes and substantiate the effort made.

  • In new contracts, expressly regulate low water and the allocation of costs.

Conclusion

Low water does not automatically excuse. Clear contractual rules on the allocation of risk create planning certainty for both sides. Please contact us if you have any questions.


As of: 23.11.2026

NIETZER Rechtsanwälte · Attorneys at Law (USA) · Heilbronn · www.unternehmensrecht.com

This article is for general information purposes only and does not replace legal advice in an individual case.